SR 3/US 19 FROM SR 54 TO FULTON COUNTY LINE
Project ID: M006040 Notice to Proceed Date:
Project Manager: Arthur Mckinley Wilson II Construction Percent Complete: 95.48%
Office: Maintenance Current Completion Date:
County: Clayton Work Completion Date:
Congressional District: 005, 013 Construction Contract Amount:
State Senate District.: 034, 044 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 060, 074, 075, 077, 078 Preconstruction Status Report
Project Type: Maintenance Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 3 to improve the roadways current low PACES rating.
ActivityProgram YearCost EstimateDate of Last Estimate
MCST (Maintenance Construction)2020$5,794,970.65 