SR 22/US 80 FROM CR 5503/CANTERBURY RD TO I-75 SB RAMP - VRU
Project ID: 0018327 Notice to Proceed Date:
Project Manager: Susan Pacheco Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Bibb Work Completion Date:
Congressional District: 002 Construction Contract Amount:
State Senate District.: 026 Construction Contractor:
State House District: 142 Preconstruction Status Report
Project Type: Safety Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
This project proposes to re-stripe and add a road transformation, rumble strips and sidewalk installation on the northside of State Route 22/Eisenhower Parkway in Bibb County. These safety improvements are expected to be delivered as a single safety funded project with the addition of the signalized Restricted Crossing U-Turn at Anthony Terrace and unsignalized Restricted Crossing U-Turn at Pine Street/Laveta Drive. In addition to the safety improvements being proposed, it is recommended that the long-term improvements include lighting and installing sidewalks on the south side of State Route 22/Eisenhower Parkway connecting the east and west of the existing sidewalks at the intersection of SR22/Eisenhower Parkway at State Route 247/Pio Nono Avenue. The local government, Macon-Bibb County, has committed to contributing the full amount of the costs required to build the sidewalks along State Route 22.
ActivityProgram YearCost EstimateDate of Last Estimate
UTL (Utilities) $100,000.00 
CST (Construction) $1,013,000.00 
PE (Preliminary Engineering)2022$620,000.00 
CST (Construction)2029$730,000.00 