project_id
0014131
SR 20 FROM CR 281/SCOTT ROAD TO CR 762/UNION HILL ROAD
Project ID:
0014131
Notice to Proceed Date:
Project Manager:
David B. Lott
Construction Percent Complete:
98.59%
Office:
Program Delivery
Current Completion Date:
County:
Cherokee
Work Completion Date:
Congressional District:
011
Construction Contract Amount:
State Senate District.:
021
Construction Contractor:
VERTICAL EARTH INCORPORATED
State House District:
023
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
0014131
Project Description:
This project is the widening and reconstruction of SR 20 in Cherokee County near Canton from east of Scott Rd to east of Union Hill Rd to six-lanes (three lanes in each direction) with a 20 foot raised median and urban shoulders. Access to side roads and driveways will be controlled by Restricted Crossing U-Turns (RCUTs) placed in the median; RCUT locations are shown in the layouts but may change based on preliminary design. Truck turnarounds are provided at certain RCUT locations based on consideration of adjacent facilities that may draw tractor trailers (factories, farms with chicken houses, landscaping or stone supply companies, etc. The total project length is about 2 miles. There are no bridges or other major structures.
Activity
Program Year
Cost Estimate
Date of Last Estimate
ROW (Right of Way)
2017
$650,000.00
3/12/2018
ROW (Right of Way)
2018
$5,000,000.00
3/12/2018
ROW (Right of Way)
2019
$4,158,500.00
3/12/2018
ROW (Right of Way)
2020
$12,733,589.00
3/12/2018
CST (Construction)
2022
$26,310,960.74
4/14/2020
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=90b59d2e-912e-4eb4-a3b2-5f8e71644ef9&Filename=0014131_L D_JAN2018.pdf
0014131_L&D_JAN2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=90b59d2e-912e-4eb4-a3b2-5f8e71644ef9&Filename=0014131_L D_JAN2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=c824223d-46d1-4638-94c6-85b5841a3269&Filename=0014131_L D_Ad_JAN2018.pdf
0014131_L&D_Ad_JAN2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=c824223d-46d1-4638-94c6-85b5841a3269&Filename=0014131_L D_Ad_JAN2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=dbad4a0a-7968-4c01-8617-d26415751f5c&Filename=0014131_CR_NOV2017.pdf
0014131_CR_NOV2017.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=dbad4a0a-7968-4c01-8617-d26415751f5c&Filename=0014131_CR_NOV2017.pdf