SR 316 @ CR 7646/OAK VALLEY ROAD
Project ID: 0013899 Notice to Proceed Date:
Project Manager: Eka Okonmkpaeto Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Gwinnett Work Completion Date:
Congressional District: 007 Construction Contract Amount:
State Senate District.: 046 Construction Contractor:
State House District: 111 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
SR 316 @ CR 7646/Oak Valley Road
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2024$585,162.832/25/2020
ROW (Right of Way)2026$6,894,000.00 
CST (Construction)2027$6,588,900.00 
Project Search (TransPI) Map
 Project Documents
 
There are no items to show in this view.