SR 5/US 78 @ SR 6/US 278
Project ID: 0013733 Notice to Proceed Date:
Project Manager: Royce Darnell Mitchell II Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Douglas Work Completion Date:
Congressional District: 013 Construction Contract Amount:
State Senate District.: 035 Construction Contractor:
State House District: 061 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
This project is located in Douglas County at the intersection of SR 5/US 78/Veterans Memorial Hwy and SR 6/US 278/Thornton Rd, approximately 1.2 miles southwest of Austell and 1 mile east of Lithia Springs. This project consists of a new location Quadrant Roadway through the Northwest quadrant of the intersection connecting SR 5 and SR 6. The project is approximately 0.9 miles in length. Minor widening will occur along SR 5 and SR 6 in order to accommodate extra capacity. SR 6 westbound would be widened to 3 thru lanes through the SR 5 and Quadrant Roadway intersections along with a dedicated right turn lane to SR 5 and the proposed Quadrant Roadway; left turn movements will be prohibited at the SR 5 at SR 6 intersection. SR 5 southbound will have 3 lanes with the outside lane turning right only to SR 6 westbound. A raised median varying from 7-14-ft as well as a 14-ft flushed median will be added along SR 5. A 16-ft raised median will be added along SR 6.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2018$1,000,000.00 
ROW (Right of Way)2024$2,130,000.001/17/2023
UTL (Utilities)2026$1,200,000.002/24/2022
CST (Construction)2026$9,793,390.092/24/2022
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports