JIMMY DELOACH PKWY EXT FM SR 21 TO SR 307
Project ID: 0008690 Notice to Proceed Date:
Project Manager: C. Andrew Hoenig Construction Percent Complete: 99.81%
Office: Innovative Prog. Delivery Current Completion Date:
County: Chatham Work Completion Date:
Congressional District: 001 Construction Contract Amount:
State Senate District.: 002 Construction Contractor: THE WALSH GROUP, LTD.
State House District: 161 Preconstruction Status Report
Project Type: New Construction Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project is sponsored by the Georgia Ports Authority and will provide enhanced roadway connection from the Ports area to I-95. The project will begin at SR 307 Bourne Avenue and continue north along new location and connect to the existing Jimmy Deloach Parkway at SR 21. It includes the construction of several bridges including over the Norfolk Southern Railroad, CSX Railroad, Crossgate Road and wetlands.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2008$633,514.372/27/2008
PE (Preliminary Engineering)2009$6,227,520.002/27/2008
UTL (Utilities)2012$3,771,220.12 
ROW (Right of Way)2012$23,010,735.816/8/2010
CST (Construction)2012$78,274,311.308/1/2011
Project Search (TransPI) Map
 Project Documents

Project Outreach Archive