SR 360 FROM NEW MACLAND ROAD/COBB TO SR 120/PAULDING
Project ID: 0006049 Notice to Proceed Date:
Project Manager: Clinton B. Ford Construction Percent Complete: 99.31%
Office: Program Delivery Current Completion Date:
County: Cobb, Paulding Work Completion Date:
Congressional District: 011, 013, 014 Construction Contract Amount:
State Senate District.: 031, 033, 037 Construction Contractor: CMES, INC.
State House District: 019, 036, 038 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
Project PI 0006049, located in Cobb and Paulding Counties, proposes to reconstruct SR 360 from a two-lane facility to a four-lane, median divided facility with curb and gutter, and sidewalks. The proposed typical section includes two 12-foot lanes in each direction, separated by a 20-foot raised grass median with curb and gutter, and five foot sidewalks on both sides of the roadway. The proposed project length is approximately 6.2 miles long with 3.1 miles in Paulding County and 3.1 miles in Cobb County. The functional classification of SR 360 is an Urban Minor Arterial. The speed limit on SR 360 is 45 mph.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2005$5,156,691.384/9/2013
ROW (Right of Way)2012$11,000,000.00 
ROW (Right of Way)2013$3,480,000.00 
PE (Preliminary Engineering)2014$1,930,000.004/9/2013
CST (Construction)2020$88,527,385.532/21/2019