SR 37 @ CR 483/THIGPEN TRAIL
Project ID: 0017960 Notice to Proceed Date:
Project Manager: Rianon Rudolfer Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Colquitt Work Completion Date:
Congressional District: 008 Construction Contract Amount:
State Senate District.: 011 Construction Contractor:
State House District: 172 Preconstruction Status Report
Project Type: Safety Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project would construct a roundabout at the intersection of SR 37 at Thigpen Trail to reduce the frequency and severity of crashes.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2022$718,000.00 
ROW (Right of Way)2025$1,750,000.0012/31/2024
CST (Construction)2026 8/16/2025
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports