SR 155/US 23 FROM ROSECLIFF DRIVE TO I-85
Project ID: 0015956 Notice to Proceed Date:
Project Manager: Chris Penuel Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: DeKalb Work Completion Date:
Congressional District: 005 Construction Contract Amount:
State Senate District.: 041 Construction Contractor:
State House District: 101 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project is 1.5 miles of the SR 155 / US 23 / Clairmont Road corridor between I-85 Northbound Exit Ramp and SR 236 / LaVista Road in DeKalb County. The proposed project modifications can be summarized as follows: PI No. 0015956 - Addition of a raised median between I-85 Northbound Exit Ramp and Audubon Drive - Addition of a through lane between I-85 NB Exit Ramp and Audubon Drive The project also proposes to install sidewalk at locations that are missing sidewalks along this section of the study corridor. Rumble strips are proposed along this corridor between Council Bluff Drive and SR 236 / LaVista Road in order to reduce ¿run off the road¿ crash types.The bridge at Interstate 85 will not be affected by the project. The I-85 northbound exit ramp terminal would have channelization, signing, marking, and traffic signal modifications.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2018$350,000.00 
ROW (Right of Way)2028$722,000.001/6/2022
UTL (Utilities)2030$595,000.007/11/2025
CST (Construction)2030$8,519,885.537/11/2025
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports