CR 742/BASS ROAD @ NS # 718357C 2 MI W OF MACON
Project ID: 0014896 Notice to Proceed Date:
Project Manager: Victor Gill Construction Percent Complete: 13.45%
Office: Program Delivery Current Completion Date:
County: Bibb Work Completion Date:
Congressional District: 008 Construction Contract Amount:
State Senate District.: 018 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 144 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project will replace the existing 26¿ wide bridge with a proposed 43¿ wide bridge over Norfolk Southern Railroad and Colonial Pipeline. The proposed bridge will be higher to meet minimum clearance over the railroad, thus there will be approximately 880¿ of roadway approach on either side of the bridge to tie back to the existing roadway grade. The roadway section will include 2-12¿ lanes and 8¿ rural shoulders (4¿ paved). The total project length is approximately 2000¿ (0.38 miles) long.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2017$1,416,000.00 
ROW (Right of Way)2020$400,000.002/20/2020
CST (Construction)2022$12,085,770.491/7/2021