SR 11/SR 49/US 41 @ NS #734080Y 1.4 MI S OF MACON
Project ID: 0013712 Notice to Proceed Date:
Project Manager: Victor Gill Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Bibb Work Completion Date:
Congressional District: 002 Construction Contract Amount:
State Senate District.: 026 Construction Contractor:
State House District: 143 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project would be constructed partially on new roadway alignment to the west of the existing US 41 bridge over Norfolk Southern railroad. The new bridge would be approximately 319 feet long, 108 feet wide, and consist of six 12-foot travel lanes and 8-foot shoulders. The new alignment typical section would consist of six 12-foot travel lanes and 10-foot (6.5 feet paved) shoulders. The proposed project is approximately 4750 feet 0.9-miles long. Right-of-way would range from 165 to 445 feet wide, with the upper limit needed to accommodate a detention structure to the west of the new bridge
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$1,992,192.57 
ROW (Right of Way)2022$1,430,000.006/17/2021
UTL (Utilities)2024$1,681,205.5910/15/2023
CST (Construction)2024 10/15/2023