SR 42/US 23 @ SR 154 & @ ARKWRIGHT PLACE
Project ID: 0012596 Notice to Proceed Date:
Project Manager: Michelle Wright Construction Percent Complete: 25.55%
Office: Program Delivery Current Completion Date:
County: Fulton Work Completion Date:
Congressional District: 005 Construction Contract Amount:
State Senate District.: 036 Construction Contractor: F. S. SCARBROUGH, LLC
State House District: 063 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project will convert the intersection of SR 42 / Moreland Avenue and Arkwright Place into a right-in/right-out (RIRO) by constructing a median to restrict all left turn movements and prohibit through movements from Arkwright Place. This project will include a signalized pedestrian crossing. The improvement is anticipated to help reduce congestion and help improve safety at the intersection.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2014$845,000.002/1/2013
ROW (Right of Way)2023$640,000.005/8/2023
CST (Construction)2025$2,909,918.0512/1/2023