SR 9 FROM FULTON COUNTY LINE TO CR 458/MCFARLAND ROAD
Project ID: 0007843 Notice to Proceed Date:
Project Manager: Eka Okonmkpaeto Construction Percent Complete: 84.37%
Office: Program Delivery Current Completion Date:
County: Forsyth Work Completion Date:
Congressional District: 007 Construction Contract Amount:
State Senate District.: 027 Construction Contractor: VERTICAL EARTH INCORPORATED
State House District: 024 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
Project CSSTP-0007-00(843) is located in southwest Forsyth County and includes the widening of SR 9/Atlanta Highway from existing two lanes to four lanes with raised median and urban shoulders. Project begins at Fulton/Forsyth County line and ends just past the intersection with CR 458/McFarland Road for a total length of 0.98 miles.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2011$776,041.2710/19/2018
PE (Preliminary Engineering)2016$1,505,000.0010/19/2018
ROW (Right of Way)2017$11,940,000.0010/20/2016
PE (Preliminary Engineering)2019$300,000.0010/19/2018
CST (Construction)2022$33,465,761.176/15/2020