SR 9 FROM WINDWARD PKWY TO FORSYTH COUNTY LINE
Project ID: 0007838 Notice to Proceed Date:
Project Manager: Eka Okonmkpaeto Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Fulton Work Completion Date:
Congressional District: 006 Construction Contract Amount:
State Senate District.: 021 Construction Contractor: VERTICAL EARTH INCORPORATED
State House District: 024, 047 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project proposes to widen SR 9 from Windward Pkwy to the Fulton/Forsyth Co. Line in Fulton Co. to a continuous four lane urban roadway with a raised median. The raised median ranges from 16 to 28 feet. Also, the proposed project consists of the reconfiguration of side roads, addition of pedestrian and bicycle facilities, traffic and operational improvements, and signal upgrades. The intersection at Bethany Bend will be re-aligned into two ninety degree intersections. Left & right turn lanes will be provided at all major intersections. The length of the proposed project is 3.04 miles.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2013$3,262,353.005/1/2019
ROW (Right of Way)2018$15,710,000.0010/20/2016
PE (Preliminary Engineering)2019$300,000.005/1/2019
PE (Preliminary Engineering)2020$1,743,605.005/1/2019
CST (Construction)2024$68,008,484.297/31/2023