Practical Construction Staging Principles


Operate as roundabout as soon as possible

Minimize number of stages

Minimize changes to traffic control when ​using parts of a circle


Avoid contra-flow traffic

Install signage, including way-finding (D and M series) before the roundabout opens

Use changeable message boards: “New Control” and “Yield Ahead”


​ ​​​​​

Goal

A well-planned construction staging process that will minimize disruption and construction fatigue.​​

 

 

Need More Information?​​

Go to Chapter 10 of the Roundabout Design Guide, which is focused on Construction Staging options.

View Guide

 

FAQs

Can roundabouts be constructed in a short time frame with little traffic impact?
Yes.​