M006682
I-75/I-85 FROM CSX #050315P TO BROOKWOOD INTERCHANGE
Project ID:
M006682
Notice to Proceed Date:
Project Manager:
Kevin Matthew Bailey
Construction Percent Complete:
79.75%
Office:
Maintenance
Current Completion Date:
County:
Fulton
Work Completion Date:
Congressional District:
005
Construction Contract Amount:
State Senate District.:
036, 039
Construction Contractor:
BALDWIN PAVING COMPANY, INC.
State House District:
056, 058, 059
Preconstruction Status Report
Project Type:
Maintenance
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
M006682
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 401 to improve the roadways current low OCI score. It was last resurfaced in 2016.
Activity
Program Year
Cost Estimate
Date of Last Estimate
MCST (Maintenance Construction)
2025
$22,572,253.10