SR 54 FROM SR 138 TO FULTON COUNTY LINE
Project ID: M006361 Notice to Proceed Date:
Project Manager: Kevin Matthew Bailey Construction Percent Complete: 14.06%
Office: Maintenance Current Completion Date:
County: Clayton Work Completion Date:
Congressional District: 005, 013 Construction Contract Amount:
State Senate District.: 034, 044 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 060, 074, 075, 076, 077 Preconstruction Status Report
Project Type: Maintenance Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 54 to improve the roadways current low PACES rating.
ActivityProgram YearCost EstimateDate of Last Estimate
MCST (Maintenance Construction)2024$5,468,515.62 
Project Search (TransPI) Map
 Project Documents
 