SR 154 FROM SR 14 TO SR 14 ALT
Project ID: M006126 Notice to Proceed Date:
Project Manager: Arthur Mckinley Wilson II Construction Percent Complete: 87.55%
Office: Maintenance Current Completion Date:
County: Fulton Work Completion Date:
Congressional District: 013 Construction Contract Amount:
State Senate District.: 028, 035 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 065 Preconstruction Status Report
Project Type: Maintenance Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 154 to improve the roadways current low PACES rating.
ActivityProgram YearCost EstimateDate of Last Estimate
MCST (Maintenance Construction)2021$603,743.50 
Project Search (TransPI) Map
 Project Documents
 