SR 34 FROM HEARD COUNTY LINE TO SR 14/SR 16 NO
Project ID: M006098 Notice to Proceed Date:
Project Manager: Arthur Mckinley Wilson II Construction Percent Complete: 97.75%
Office: Maintenance Current Completion Date:
County: Coweta Work Completion Date:
Congressional District: 003 Construction Contract Amount:
State Senate District.: 028 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 070 Preconstruction Status Report
Project Type: Maintenance Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 28 to improve the roadways current low PACES rating.
ActivityProgram YearCost EstimateDate of Last Estimate
MCST (Maintenance Construction)2022$3,840,980.34 
Project Search (TransPI) Map