713300-
713300-
I-285 @ BOULDERCREST ROAD
Project ID:
713300-
Notice to Proceed Date:
Project Manager:
Obi Ezenekwe
Construction Percent Complete:
60.26%
Office:
Program Delivery
Current Completion Date:
County:
DeKalb
Work Completion Date:
Congressional District:
005
Construction Contract Amount:
State Senate District.:
044
Construction Contractor:
C. W. MATTHEWS CONTRACTING CO., INC.
State House District:
090
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
I-285 @ BOULDERCREST ROAD
Project ID:
713300-
Notice to Proceed Date:
Project Manager:
Obi Ezenekwe
Construction Percent Complete:
0.00%
Office:
Program Delivery
Current Completion Date:
County:
DeKalb
Work Completion Date:
Congressional District:
005
Construction Contract Amount:
State Senate District.:
044
Construction Contractor:
C. W. MATTHEWS CONTRACTING CO., INC.
State House District:
090
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
713300-
713300-
Project Description:
The project will include a CD roadway system between the I-675/I-285 interchange and the I-285/Bouldercrest Road interchange. On Bouldercrest Road, the project will extend from approximately 220¿ south of Sugar Creek Golf Drive to approximately 525¿ north of Continental Way. On I-285, the project would extend from the I-675 northbound exit ramp bridge over I-285 to just west of the I-285 bridge over Sugar Creek. The reconstruction of the I-285/Bouldercrest Road interchange will require replacing the existing Bouldercrest Road bridge over I-285. The new bridge will have six 12-foot travel lanes (two southbound through lanes, two southbound left-turn lanes and two northbound through lanes), 6-foot sidewalks on both sides and 4-foot wide bicycle lanes on both sides. North of the interchange, Bouldercrest Road will transition to the existing 5-lane section north of Continental Way.
Project Description:
The project will include a CD roadway system between the I-675/I-285 interchange and the I-285/Bouldercrest Road interchange. On Bouldercrest Road, the project will extend from approximately 220¿ south of Sugar Creek Golf Drive to approximately 525¿ north of Continental Way. On I-285, the project would extend from the I-675 northbound exit ramp bridge over I-285 to just west of the I-285 bridge over Sugar Creek. The reconstruction of the I-285/Bouldercrest Road interchange will require replacing the existing Bouldercrest Road bridge over I-285. The new bridge will have six 12-foot travel lanes (two southbound through lanes, two southbound left-turn lanes and two northbound through lanes), 6-foot sidewalks on both sides and 4-foot wide bicycle lanes on both sides. North of the interchange, Bouldercrest Road will transition to the existing 5-lane section north of Continental Way.
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
1999
$4,112,000.00
10/19/2018
ROW (Right of Way)
2014
$700,000.00
PE (Preliminary Engineering)
2014
$120,000.00
10/19/2018
PE (Preliminary Engineering)
2017
$1,000,000.00
10/19/2018
ROW (Right of Way)
2018
$22,730,000.00
PE (Preliminary Engineering)
2019
$6,400,000.00
10/19/2018
CST (Construction)
2022
$94,633,999.53
2/11/2021
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=019c55fb-03a6-4af9-804d-1a2ee5728ad3&Filename=713300-_REVCR_DEC2012.pdf
713300-_REVCR_DEC2012.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=019c55fb-03a6-4af9-804d-1a2ee5728ad3&Filename=713300-_REVCR_DEC2012.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=319d3575-ee8e-4f12-b99f-9fb6f2ce4533&Filename=713300-_L D_Ads_JUL2018.pdf
713300-_L&D_Ads_JUL2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=319d3575-ee8e-4f12-b99f-9fb6f2ce4533&Filename=713300-_L D_Ads_JUL2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=450c5296-d620-4a54-94c6-466fc2239ffe&Filename=713300-_CR_SEP2001.pdf
713300-_CR_SEP2001.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=450c5296-d620-4a54-94c6-466fc2239ffe&Filename=713300-_CR_SEP2001.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=e517a758-94cc-4f0d-b0aa-9c5dd35ed3c7&Filename=713300-_L D_JUN2018.pdf
713300-_L&D_JUN2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=e517a758-94cc-4f0d-b0aa-9c5dd35ed3c7&Filename=713300-_L D_JUN2018.pdf