SR 12/US 278 FM COVINGTON CITY LIMITS TO E OF SR 142
Project ID: 231630- Notice to Proceed Date:
Project Manager: Bruce G. Anderson Jr. Construction Percent Complete: 93.09%
Office: Program Delivery Current Completion Date:
County: Newton Work Completion Date:
Congressional District: 004, 010 Construction Contract Amount:
State Senate District.: 017 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 112 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
This project consists of the widening and reconstruction of State Route 12/US Route 278 from mile post 7.97 to mile post 10.43. The roadway will consist of two 12' lanes in each direction separated by a 24' raised grassed median with 10' rural shoulders of which 6.5' is paved. Also included in this project is a round-a-bout at the intersection of State Route 12 and State Route 142. A traffic signal will also be installed at the intersection of SR12 and Elks Club Road (CR 156). This project will be constructed using stage construction.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)1999$703,750.00 
ROW (Right of Way)2014$2,136,000.002/14/2014
PE (Preliminary Engineering)2014$400,558.61 
CST (Construction)2017$10,240,969.324/5/2016