NORTH PEACHTREE ROAD FROM DUNWOODY CROSSING TO BARCLAY DRIVE
Project ID: 0021596 Notice to Proceed Date:
Project Manager: Felecia Basolo Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: DeKalb Work Completion Date:
Congressional District: 004 Construction Contract Amount:
State Senate District.: 040 Construction Contractor:
State House District: 080 Preconstruction Status Report
Project Type: New Construction Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The project is located within the City of Dunwoody. It would be a shared use path beginning just north of Interstate 285 northward to Dunwoody¿s Brook Run Park.
ActivityProgram YearCost EstimateDate of Last Estimate
ROW (Right of Way) $1,089,668.00 
PE (Preliminary Engineering)2026$2,106,446.00 
UTL (Utilities)2028$711,621.00 
CST (Construction)2028$12,938,572.00 
Project Search (TransPI) Map
 Project Documents
 
There are no items to show in this view.