I-16 FROM I-95/CHATHAM TO SR 67/BULLOCH
Project ID: 0020739 Notice to Proceed Date:
Project Manager: Rick O'Hara Construction Percent Complete: 0.00%
Office: P3 Current Completion Date:
County: Bryan, Bulloch, Chatham, Effingham Work Completion Date:
Congressional District: 001, 012 Construction Contract Amount:
State Senate District.: 001, 004 Construction Contractor:
State House District: 159, 160, 164 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
ActivityProgram YearCost EstimateDate of Last Estimate
ROW (Right of Way)2026$500,000.002/25/2026
CST (Construction)2026$525,000,000.002/25/2026
Project Search (TransPI) Map
 Project Documents
 