Welcome to The GDOT
applications
GeoPI
Project Information
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
Welcome to The GDOT
Currently selected
Recent
project_id
0017815
CHATTAHOOCHEE GREENWAY FROM SR 120 TO CAULEY CREEK PARK
Project ID:
0017815
Notice to Proceed Date:
Project Manager:
Shuhui Yang
Construction Percent Complete:
0.00%
Office:
Program Delivery
Current Completion Date:
County:
Fulton
Work Completion Date:
Congressional District:
007
Construction Contract Amount:
State Senate District.:
048
Construction Contractor:
State House District:
050
Preconstruction Status Report
Project Type:
Enhancement
Construction Status Report
Project Status:
Construction Work Program
More Information...
Right of Way Authorization:
Contact Us
project_id
0017815
Project Description:
The Chattahoochee Greenway is a 1-mile long, 10-foot wide shared use path along the Chattahoochee River, within the City of Johns Creek, from SR 120/Abbotts Bridge Road to Cauley Creek Park.
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2021
$1,100,000.00
11/11/2025
PE (Preliminary Engineering)
2026
$1,062,500.00
11/11/2025
ROW (Right of Way)
2027
$100,000.00
CST (Construction)
2028
$4,750,000.00
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=6086224a-f330-4feb-a638-b1e628757d4b&Filename=0017815_CR_NOV2022.pdf
0017815_CR_NOV2022.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=6086224a-f330-4feb-a638-b1e628757d4b&Filename=0017815_CR_NOV2022.pdf