SR 5 FROM WASH WILSON ROAD TO OLD FLOWERS ROAD - PHASE I
Project ID: 0017038 Notice to Proceed Date:
Project Manager: Ethan Mobley Construction Percent Complete: 46.71%
Office: Program Delivery Current Completion Date:
County: Fannin Work Completion Date:
Congressional District: 009 Construction Contract Amount:
State Senate District.: 051 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 007 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project proposes to widen the existing SR 5 in Fannin County, Georgia, beginning at Wash Wilson Rd and ending approximately 1.52 miles north near the intersection of Old Flowers Road. The project would widen SR 5 to four (4) lanes (12-foot outside lane & 11-foot inside lane) with a 14-foot center turn lane from Wash Wilson Rd to McCaysville Industrial Drive. The project would then transition to two 12-foot lanes to match the existing pavement ending at Old Flowers Road. Outside shoulders would be 10-foot wide (6.5 feet of paved shoulder including a 4-foot, 2-inch bike lane) for both sections.
ActivityProgram YearCost EstimateDate of Last Estimate
CST (Construction)2020$22,746,243.15 