CAMPBELLTON RD FROM CR 485/ENON RD TO CS 2952/CAMPGROUND RD
Project ID: 0015664 Notice to Proceed Date:
Project Manager: Susan Pacheco Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Fulton Work Completion Date:
Congressional District: 006 Construction Contract Amount:
State Senate District.: 035, 038 Construction Contractor:
State House District: 055, 061, 065 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project will construct pedestrian accommodations where needed and minor widening along State Route 154/State Route 166/Campbellton Road from Enon Road to Campground Road, in the City of Atlanta in Fulton County, a distance of 2.1 miles. These improvements will address the need for sidewalks, improved pedestrian accommodations, and minor operational improvements throughout the project corridor.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2019$45,000.00 
ROW (Right of Way)2024$4,894,000.0011/2/2020
UTL (Utilities)2028$1,055,325.005/26/2026
CST (Construction)2028$11,294,365.275/26/2026