SR 3/US 41 FROM CS 1704/TECH PKWY TO CS 696/HEMPHILL AVE
Project ID:
0015288
Notice to Proceed Date:
Project Manager:
Michelle Wright
Construction Percent Complete:
0.00%
Office:
Program Delivery
Current Completion Date:
County:
Fulton
Work Completion Date:
Congressional District:
005
Construction Contract Amount:
State Senate District.:
039
Construction Contractor:
EXCELLERE CONSTRUCTION, LLC
State House District:
056
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
0015288
Project Description:
The project proposes improvements at the intersection cluster of State Route 3 (Northside Drive), 14th Street, and Hemphill Avenue which will be simplified to provide additional flexibility for signal timing.
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2017
$1,306,309.43
ROW (Right of Way)
2024
$480,000.00
2/20/2024
CST (Construction)
2026
$1,940,781.78
3/12/2025
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=d147eb2b-7853-4c95-b52c-b8c2e20d5bf1&Filename=0015288_L D_DEC2022.pdf
0015288_L&D_DEC2022.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=d147eb2b-7853-4c95-b52c-b8c2e20d5bf1&Filename=0015288_L D_DEC2022.pdf