SR 82 @ MIDDLE OCONEE RIVER 5 MI NE OF STATHAM
Project ID: 0013819 Notice to Proceed Date:
Project Manager: Corey Jackson Construction Percent Complete: 93.31%
Office: Program Delivery Current Completion Date:
County: Barrow, Jackson Work Completion Date:
Congressional District: 009, 010 Construction Contract Amount:
State Senate District.: 047 Construction Contractor: GEORGIA BRIDGE AND CONCRETE, LLC
State House District: 120 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project will replace the existing SR 82 bridge over the Middle Oconee River. A new bridge will be constructed on existing alignment with implementation of an offsite detour. The proposed roadway typical section will be two 12-foot lanes with 10-foot (6.5-ft paved) outside shoulders. The proposed bridge will have two 12-foot lanes and 8-foot shoulders.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$1,294,845.67 
ROW (Right of Way)2020$360,000.005/22/2020
CST (Construction)2022$6,528,447.658/28/2020