project_id
0013733
SR 5/US 78 @ SR 6/US 278
Project ID:
0013733
Notice to Proceed Date:
Project Manager:
Obi Ezenekwe
Construction Percent Complete:
%
Office:
Program Delivery
Current Completion Date:
County:
Douglas
Work Completion Date:
Congressional District:
013
Construction Contract Amount:
State Senate District.:
035
Construction Contractor:
State House District:
061
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Construction Work Program
More Information...
Right of Way Authorization:
Contact Us
project_id
0013733
Project Description:
This project plans to improve the current and future traffic mobility needs, reduce congestion, reduce the frequency of crashes, and improve operations for trucks and passenger vehicles operations at the intersection of State Route (SR)5/US 78 and SR6/US 278 with a Quadrant Intersection that has limited access.
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2018
$1,000,000.00
ROW (Right of Way)
2024
$2,926,000.00
12/3/2021
UTL (Utilities)
2026
$1,200,000.00
2/24/2022
CST (Construction)
2026
$9,793,390.09
2/24/2022
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
http://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=f93de201-62ba-4d0d-aef4-9916074672b5&Filename=0013733_CR_OCT2020.pdf
0013733_CR_OCT2020.pdf
http://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=f93de201-62ba-4d0d-aef4-9916074672b5&Filename=0013733_CR_OCT2020.pdf