Project Information
Welcome to The GDOT
applications
GeoPI
Project Information
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
Welcome to The GDOT
Currently selected
Recent
project_id
0013715
SR 10 LOOP EB & WB @ MIDDLE OCONEE RIVER 5 MI E OF BOGART
Project ID:
0013715
Notice to Proceed Date:
Project Manager:
Corey Jackson
Construction Percent Complete:
38.25%
Office:
Program Delivery
Current Completion Date:
County:
Clarke
Work Completion Date:
Congressional District:
010
Construction Contract Amount:
State Senate District.:
047
Construction Contractor:
E. R. SNELL CONTRACTOR, INC.
State House District:
120
Preconstruction Status Report
Project Type:
Replacement
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
0013715
Project Description:
The project will replace both the existing Eastbound and Westbound bridges. Construction will be staged to allow traffic to be detoured onsite during construction. The proposed roadway typical section in both EB and WB directions will be two 12-foot travel lanes with 12-foot (10-ft. paved) outside shoulder and 6-foot (4-ft. paved) inside shoulder. A 40-foot depressed median will be between the EB and WB roadways. The proposed bridge section on each bridge will be two 12-foot travel lanes with 10-foot outside shoulders and 18.5-foot inside shoulders. The construction staging and maintenance of traffic requirements will result in a final bridge extending the full width of the roadway section.
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2016
$1,550,000.00
ROW (Right of Way)
2020
$160,000.00
CST (Construction)
2023
$15,374,732.45
8/28/2020
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=3d0885ff-84a7-4991-a4a1-72d4ba322e27&Filename=0013715_L D_JUN2020.pdf
0013715_L&D_JUN2020.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=3d0885ff-84a7-4991-a4a1-72d4ba322e27&Filename=0013715_L D_JUN2020.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=a156d294-006a-4273-9b4e-28b5c790032a&Filename=0013715_L D_ADs_JUL2020.pdf
0013715_L&D_ADs_JUL2020.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=a156d294-006a-4273-9b4e-28b5c790032a&Filename=0013715_L D_ADs_JUL2020.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=ced1ed01-9a3c-4249-a857-cc6b26aa6df9&Filename=0013715_CR_MAY2018.pdf
0013715_CR_MAY2018.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=ced1ed01-9a3c-4249-a857-cc6b26aa6df9&Filename=0013715_CR_MAY2018.pdf