SR 10 LOOP EB & WB @ MIDDLE OCONEE RIVER 5 MI E OF BOGART
Project ID: 0013715 Notice to Proceed Date:
Project Manager: Corey Jackson Construction Percent Complete: 38.25%
Office: Program Delivery Current Completion Date:
County: Clarke Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 047 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 120 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project will replace both the existing Eastbound and Westbound bridges. Construction will be staged to allow traffic to be detoured onsite during construction. The proposed roadway typical section in both EB and WB directions will be two 12-foot travel lanes with 12-foot (10-ft. paved) outside shoulder and 6-foot (4-ft. paved) inside shoulder. A 40-foot depressed median will be between the EB and WB roadways. The proposed bridge section on each bridge will be two 12-foot travel lanes with 10-foot outside shoulders and 18.5-foot inside shoulders. The construction staging and maintenance of traffic requirements will result in a final bridge extending the full width of the roadway section.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$1,550,000.00 
ROW (Right of Way)2020$160,000.00 
CST (Construction)2023$15,374,732.458/28/2020