SR 400 @ SR 369
Project ID: 0013369 Notice to Proceed Date:
Project Manager: Kesha Wynn Construction Percent Complete: 97.04%
Office: Program Delivery Current Completion Date:
County: Forsyth Work Completion Date:
Congressional District: 006 Construction Contract Amount:
State Senate District.: 027 Construction Contractor: FORSYTH COUNTY
State House District: 028 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project proposes to upgrade the existing at-grade signalized intersection of US 19/SR 400 and SR 369/Browns Bridge Road to a grade-separated, partial cloverleaf interchange. The project also includes widening and improvements on SR 369 from Coal Mountain Road to east of SR 306/Keith Bridge Road. Total project length is 0.9 miles for the interchange portion of the project and 2.036 miles for the SR 369 widening portion.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$1,093,008.0010/19/2018
ROW (Right of Way)2018$10,600,000.00 
PE (Preliminary Engineering)2019$55,000.0010/19/2018
UTL (Utilities)2020$664,235.006/7/2019
CST (Construction)2020$21,510,626.384/12/2019