REDWINE ROAD & STARRS MILL SCHOOL COMPLEX MULTI-USE PATH
Project ID: 0012624 Notice to Proceed Date:
Project Manager: Antoniette K Moseley Construction Percent Complete: 99.11%
Office: Program Delivery Current Completion Date:
County: Fayette Work Completion Date:
Congressional District: 003 Construction Contract Amount:
State Senate District.: 016 Construction Contractor: FAYETTE COUNTY
State House District: 073, 074 Preconstruction Status Report
Project Type: Enhancement Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
A 10-ft wide multi-use path along Redwine Road between Birkdale Drive and Newhaven Drive (a distance of 4,300 feet) with a similar path between Preserve Place and Foreston Place (a distance of 3,600 feet. Includes crossing improvements near Old Ivy / Carnoustie Way and other path improvements along Redwine Road as deemed appropriate and feasible.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2014$184,080.002/1/2013
ROW (Right of Way)2017$250,000.00 
CST (Construction)2017$2,063,028.04 
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports