SR 92 FM CS 611/MALONE RD TO CS 519/NEBO RD-SEGMENT 1-PH IV
Project ID: 0007691 Notice to Proceed Date:
Project Manager: Oluchukwu Eziogonnaya Anyaebosi Construction Percent Complete: 98.53%
Office: Program Delivery Current Completion Date:
County: Douglas, Paulding Work Completion Date:
Congressional District: 013, 014 Construction Contract Amount:
State Senate District.: 030, 031, 035 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 019, 064, 066 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
Project will widen SR 92 starting at Malone Road in Douglas County and go north to Nebo Road in Paulding County. From Malone Road to Bill Carruth Parkway, the project would widen the existing SR 92 from 1-lane in each direction to 3-lanes in each direction with a 20' to 24' raised median. From Bill Carruth Parkway to Nebo Road, two lanes is proposed in each direction with a 20' to 24' raised median.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2007$2,874,979.51 
ROW (Right of Way)2014$24,953,473.001/17/2013
PE (Preliminary Engineering)2014$2,140,202.98 
CST (Construction)2017$66,137,869.648/17/2016