Home
Board
Employment
Blog
News
Contact Us
Project Information
Welcome to The GDOT
applications
GeoPI
Project Information
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
Welcome to The GDOT
Currently selected
Recent
project_id
0007414
CR 90/COLERAIN ROAD FM W OF I-95 TO E OF KINGS BAY ROAD
Project ID:
0007414
Notice to Proceed Date:
Project Manager:
Cassius Octavius Edwards
Construction Percent Complete:
93.07%
Office:
Program Delivery
Current Completion Date:
County:
Camden
Work Completion Date:
Congressional District:
001
Construction Contract Amount:
State Senate District.:
3
Construction Contractor:
PLANT IMPROVEMENT CO., INC.
State House District:
180
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Complete
More Information...
Right of Way Authorization:
Contact Us
project_id
0007414
Project Description:
The proposed Colerain Road/ CR 90 typical section is two 12-foot lanes in each direction separated by a 20-foot raised median. The purpose of this Revised Concept Report is to change the urban shoulder section from 4-foot bike lanes and 5-foot sidewalks on both sides to a 10-foot multi-use path on the north side and a 5-foot sidewalk on the soufu side of proposed Colerain Road as a cost savings measure while meeting Camden County's bike route system requirements for Colerain Road. The rural shoulder section from 2664 feet west of I-95 to relocated Brazell Road is changed to an urban section to eliminate the need for barrier separation between the travel lanes and the multi-use path on the proposed bridge over I-95. The rural shoulder section from 3800 feet west of Wmding Road to Winding Road is changed to an urban section. The substantial residential development planned for this area would use the sidewalks to the nearby county high school. The rural shoulder section from Wmd
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2007
$1,162,324.67
3/27/2014
ROW (Right of Way)
2013
$6,530,000.00
5/1/2013
PE (Preliminary Engineering)
2015
$50,000.00
3/27/2014
CST (Construction)
2017
$47,576,129.59
12/2/2015
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
Approved Concept Reports
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=1a206ba0-4a64-4b2e-b3fe-fe7c0063c9bc&Filename=0007414_L D_APR2013.pdf
0007414_L&D_APR2013.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=1a206ba0-4a64-4b2e-b3fe-fe7c0063c9bc&Filename=0007414_L D_APR2013.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=a2595976-201e-4b5e-b19e-996c593e5a97&Filename=0007414_L D_AD_APR2013.pdf
0007414_L&D_AD_APR2013.pdf
https://www.dot.ga.gov/_layouts/GDOT.SharePoint.CustomHttpHandlers/PWDocumentDownloadHandler.ashx?DocGUID=a2595976-201e-4b5e-b19e-996c593e5a97&Filename=0007414_L D_AD_APR2013.pdf