SR 53 @ BROWNLEE MOUNTAIN ROAD/PLAINVILLE ROAD
Project ID: 0005317 Notice to Proceed Date:
Project Manager: Ethan Mobley Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Gordon Work Completion Date:
Congressional District: 011 Construction Contract Amount:
State Senate District.: 052 Construction Contractor: BARTOW PAVING COMPANY, INC.
State House District: 005 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The intersection of SR 53 @ Brownlee Road/Plainville Road will be improved to address safety concerns through the installation of a stop controlled Restricted Crossing U-Turn (RCUT) intersection to prevent through movement from the minor roadway crossing the mainline.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2021$400,000.00 
ROW (Right of Way)2023$430,000.009/23/2021
CST (Construction)2025$4,577,371.727/17/2024
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports