SR 40 FM E OF ST MARYS RIVER TRIB TO E OF CR 66/COLERAIN RD
Project ID: 0000820 Notice to Proceed Date:
Project Manager: Cassius Octavius Edwards Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Camden, Charlton Work Completion Date:
Congressional District: 001 Construction Contract Amount:
State Senate District.: 003 Construction Contractor:
State House District: 174 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
State Route (SR) 40 is a major east-west corridor in southeast Georgia, connecting Folkston on the west with Kingsland, I-95, & St. Marys on the east. SR 40, which is designated as a hurricane evacuation route, has been identified for widening as part of the Governor¿s Road Improvement Program (GRIP). The project begins on the east side of the City of Folkston at the intersection of SR 40 with SR 40 connector/Indian Trail/US 301 Connector & extends to the I-95 Interchange at Exit 6 in Camden County. The GRIP project would widen the 29-mile long SR 40 corridor to four lanes, most of it divided by a 4-foot flush median & widen an 11.47-mile portion of the SR 40 corridor between milepost 5.21 in Charlton County to County Route (CR) 66, Colerain Road MP 10.12 in Camden County. Five Box Bridge culverts will be lengthen they include 039-0059-0, 039- 0014-0, 039-060-0, 0390061-0, and 039-0062-0.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2003$5,448,897.84 
ROW (Right of Way)2028$3,600,000.001/31/2024
UTL (Utilities)2030$3,765,897.302/7/2024
CST (Construction)2030$47,752,506.2110/15/2023