I-75 FM N OF SR 133 TO COOK COUNTY LINE - PHASE II
Project ID: 0000762 Notice to Proceed Date:
Project Manager: Clinton B. Ford Construction Percent Complete: 95.06%
Office: Program Delivery Current Completion Date:
County: Lowndes Work Completion Date:
Congressional District: 008 Construction Contract Amount:
State Senate District.: 008 Construction Contractor: REAMES AND SON CONSTRUCTION COMPANY, INC.
State House District: 175 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
The I-75/SR7 (Shiloh Road/North Valdosta Road) interchange reconstruction begins on Shiloh Road just east of the Frank¿s Creek bridge. With proposed improvements, the existing two-lane Shiloh Road would transition to and become a four-lane divided roadway with a 20-foot raised concrete median and rural 6 1/2-foot outside paved shoulders. The existing I-75 southbound on and off-ramps constructed under Project NH 75-1(203), P.I. No. 410500 would be tied to the proposed SR7 improvements. The project would include a new bridge over I-75 and reconstruct the I-75 northbound on and off-ramps as a conventional diamond interchange. The I-75/SR7 interchange reconstruction on SR7 (N. Valdosta Road) ends just west of the existing signalized intersection at Coleman Road (CR553). The project would tie to the existing four-lane divided rural roadway with a forty-foot depressed grass median.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2005$3,651,924.96 
ROW (Right of Way)2014$20,000,000.0010/23/2013
CST (Construction)2017$52,424,926.562/23/2017