SR 6 FROM SR 5 TO FULTON COUNTY LINE
Project ID: M006333 Notice to Proceed Date:
Project Manager: Kevin Matthew Bailey Construction Percent Complete: 84.89%
Office: Maintenance Current Completion Date:
County: Douglas Work Completion Date:
Congressional District: 013 Construction Contract Amount:
State Senate District.: 035 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 061 Preconstruction Status Report
Project Type: Maintenance Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 6 to improve the roadways current OCI Score.
ActivityProgram YearCost EstimateDate of Last Estimate
MCST (Maintenance Construction)2023$6,895,484.63 