project_id
311465-
I-75/I-475 INTERCHANGE @ CR 740/HARTLEY BRIDGE ROAD
Project ID:
311465-
Notice to Proceed Date:
Project Manager:
Theresa R Holder
Construction Percent Complete:
96.99%
Office:
Urban Design
Current Completion Date:
County:
Bibb
Work Completion Date:
Congressional District:
008
Construction Contract Amount:
State Senate District.:
018
Construction Contractor:
THE WALSH GROUP, LTD.
State House District:
142
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Complete
More Information...
Right of Way Authorization:
Contact Us
project_id
311465-
Project Description:
This project proposes to widen I-75 from approximately 1.7 miles south of Hartley Bridge Road to the I-475/I-75 split from three to five 12-foot travel lanes in both directions; to reconstruct the I-475/I-75 Interchange; and to build Collector-Distributor Roads between Hartley Bridge and the I-475/I-75 Interchange. It will also complete the interchange construction at Hartley Bridge Road CT. 1.
Activity
Program Year
Cost Estimate
Date of Last Estimate
ROW (Right of Way)
2001
$2,103,000.00
CST (Construction)
2006
$114,987,392.48
1/20/2006