SR 162 FROM CR 511/BROWN BRIDGE ROAD TO CR 34/OLD SALEM ROAD
Project ID: 231210- Notice to Proceed Date:
Project Manager: Frank Childs Jr Construction Percent Complete: 24.24%
Office: Program Delivery Current Completion Date:
County: Newton Work Completion Date:
Congressional District: 013 Construction Contract Amount:
State Senate District.: 042, 043 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 113 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
Project 231210- & 0013628, SR 162/Salem Road involves widening Salem Road from just south of Brown Bridge Road in Newton County to Flat Shoals Road in Rockdale County from the existing 2-lane roadway to a 4-lane roadway (2 lanes in each direction). Salem Road from Flat Shoals Road to the I-20 ramps will be widened from its existing 4-lane roadway to a 6-lane roadway. A 16-ft raised is proposed for the entire length of the project. A 12-ft shoulder that includes a 5-ft sidewalk will be on the east side. A 20-ft shoulder including a 10-ft shared use path, is proposed on the west side throughout the SR 162 corridor.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)1999$37,724.9310/19/2018
PE (Preliminary Engineering)2005$2,300,000.0010/19/2018
ROW (Right of Way)2018$11,675,000.005/18/2020
PE (Preliminary Engineering)2019$2,305,000.0010/19/2018
ROW (Right of Way)2022$9,755,000.005/18/2020
CST (Construction)2025$66,378,398.0410/4/2023
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports