SR 10 LOOP SB & NB @ NORTH OCONEE RIVER 1.4 MI S OF ATHENS
Project ID: 0019265 Notice to Proceed Date:
Project Manager: Albert V. Shelby III Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Clarke Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 046, 047 Construction Contractor:
State House District: 122 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
Bridge Replacement at SR 10 Loop SB & NB over North Oconee River.
ActivityProgram YearCost EstimateDate of Last Estimate
UTL (Utilities)2052$100,000.00 
ROW (Right of Way)2052$140,000.00 
PE (Preliminary Engineering)2052$1,400,000.00 
CST (Construction)2052$16,800,000.00 
Project Search (TransPI) Map
 Project Documents
 
There are no items to show in this view.