0017126
I-285 @ SR 141
Project ID:
0017126
Notice to Proceed Date:
Project Manager:
Rick O'Hara
Construction Percent Complete:
100.00%
Office:
Innovative Prog. Delivery
Current Completion Date:
County:
DeKalb
Work Completion Date:
Congressional District:
006
Construction Contract Amount:
State Senate District.:
040
Construction Contractor:
E. R. SNELL CONTRACTOR, INC.
State House District:
080
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Complete
More Information...
Right of Way Authorization:
Contact Us
project_id
0017126
Project Description:
PI# 0017126 will provide dedicated exit lanes and reconfigure the interchange ramps to reduce the bottleneck from I-285 westbound to Peachtree Industrial Boulevard (PIB). The existing single lane westbound exit from I-285 to PIB northbound and southbound will be reconstructed into a two-lane exit facility. To further enhance continuous flow, the existing horizontal curvature of the westbound I-285 to northbound PIB exit ramp will be flattened and the access to Flowers Road, a local City of Doraville street, will be eliminated.
Activity
Program Year
Cost Estimate
Date of Last Estimate
CST (Construction)
2021
$21,992,609.00
11/3/2020