SR 7/SR 127/US 41 @ BIG INDIAN CREEK IN PERRY
Project ID: 0015553 Notice to Proceed Date:
Project Manager: Damian McSwain Construction Percent Complete: 15.72%
Office: Program Delivery Current Completion Date:
County: Houston Work Completion Date:
Congressional District: 008 Construction Contract Amount:
State Senate District.: 020 Construction Contractor: SOUTHEASTERN SITE DEVELOPMENT, INC.
State House District: 146, 148 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project located along SR 7/SR 127/US 41 in the city of Perry, would replace the existing bridge over Big Indian Creek. The bridge will consist of five 12-foot lanes (two in each direction and a center turn lane) and 4-foot bike lanes adjacent to the roadway with sidewalks in both directions. The proposed roadway would have a similar typical section consisting of five 12-foot lanes (two in each direction and a center turn lane), with 4-foot bike lanes an urban shoulder and sidewalk on each side. The project has a total project length of 0.284 miles.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2019$2,452,000.00 
ROW (Right of Way)2024$750,000.004/13/2024
CST (Construction)2026$9,575,500.135/17/2024
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports