SR 520BU @ FLINT RIVER IN ALBANY
Project ID: 0013992 Notice to Proceed Date:
Project Manager: Matthew Sanders Construction Percent Complete: 56.11%
Office: Program Delivery Current Completion Date:
County: Dougherty Work Completion Date:
Congressional District: 002 Construction Contract Amount:
State Senate District.: 012 Construction Contractor: SOUTHERN CONCRETE CONSTRUCTION CO., INC.
State House District: 153, 154 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project has an approximate total length of 0.22 miles, and will replace the existing bridge on SR 520BU/US 82BU over the Flint River in Albany, Georgia with a new bridge consisting of four 12ft lanes, 2ft gutters, and a 5.5ft sidewalk on the north side of the bridge and 12.0ft barrier separated, shared use path on the south side of the bridge. The existing roadway will be detoured in order to construct the proposed bridge in the same location as the existing bridge. The existing westbound right turn lane and left turn lane will be lengthened in order to provide a longer taper and queue length.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2017$2,204,000.00 
ROW (Right of Way)2022$170,000.006/10/2022
CST (Construction)2024$23,230,280.8212/19/2022
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports