Project ID: 0007842 Notice to Proceed Date:
Project Manager: Adolfo Villarroel Construction Percent Complete: 0.00%
Office: Program Delivery Current Completion Date:
County: Fulton Work Completion Date:
Congressional District: 006 Construction Contract Amount:
State Senate District.: 038 Construction Contractor:
State House District: 067, 068 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project is approximately 1.79 miles along SR 138 Jonesboro Road from Goodson Connector to Buffington Road. The project includes the modification of the SR 138 and I-85 interchange to a diverging diamond interchange. The northbound entrance ramp to I-85 and the southbound exit ramp to Jonesboro Rd/ SR 138 will be lengthened to improve capacity and merging operations. Jonesboro Rd/ SR 138 will add a shared through and right turn lanes from Goodson Connector to Lester Road, providing 3 lanes in each direction. The project will also interconnect and upgrade the signals along SR 138 from Goodson Connector on the west to Buffington Road to the east of the interchange. Landscaping and pedestrian lighting will be improved along Jonesboro Rd/SR 138. The entire project is located in Fulton County and within the city limits of Union City.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2014$3,154,628.8210/19/2018
PE (Preliminary Engineering)2019$1,793,549.8410/19/2018
ROW (Right of Way)2021$14,240,000.002/23/2026
PE (Preliminary Engineering)2021$1,000,000.0010/19/2018
UTL (Utilities)2028$2,492,600.002/23/2026
CST (Construction)2028$62,597,286.592/23/2026