Home
Board
Employment
Blog
News
Contact Us
Project Information
Welcome to The GDOT
applications
GeoPI
Project Information
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
Welcome to The GDOT
Currently selected
Recent
project_id
M006446
I-285 FROM CR 5158/HENDERSON MILL ROAD TO SR 8
Project ID:
M006446
Notice to Proceed Date:
Project Manager:
Kevin Matthew Bailey
Construction Percent Complete:
32.42%
Office:
Maintenance
Current Completion Date:
County:
DeKalb
Work Completion Date:
Congressional District:
004
Construction Contract Amount:
State Senate District.:
040, 041
Construction Contractor:
CAUSIE CONTRACTING, INC.
State House District:
081, 086
Preconstruction Status Report
Project Type:
Maintenance
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
M006446
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of I-285 to improve the roadways current low PACES rating.
Activity
Program Year
Cost Estimate
Date of Last Estimate
MCST (Maintenance Construction)
2025
$4,662,438.76
Project Search (TransPI) Map
Project Documents
FILE_PATH
FILE_NAME
PATH
There are no items to show in this view.