SR 120 FROM JONES CREEK COMMONS TO S OF BOLES ROAD
Project ID: 721000- Notice to Proceed Date:
Project Manager: Achor Njoku Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Fulton Work Completion Date:
Congressional District: 007 Construction Contract Amount:
State Senate District.: 048 Construction Contractor:
State House District: 050 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
The proposed project would widen State Route (SR) 120/Abbotts Bridge Road from SR 141/Medlock Bridge Road to Peachtree Industrial Boulevard from two to four through lanes.The total project length is approximately 2.5 miles, which includes a 1500¿ tie-in to SR 120 west of SR 141 and a 1000¿ tie-in east of Peachtree Industrial Boulevard. Both SR 141 and Peachtree Industrial Boulevard would be improved and widened for approximately 1000¿ in each direction approaching SR 120. Parsons Road would also be improved and widened for 1250¿ south of SR 120, and Boles Road would be improved for 1000¿ north of SR 120. All other side roads would be improved to a maximum of 500¿ from SR 120. The existing SR 120 bridge would be widened and/or reconstructed across the Chattahoochee River. All signalized intersections would be modified. Existing ROW within the project corridor are approximately 60 to 130 feet. Proposed ROW would be approximately 104 to 140 feet.
ActivityProgram YearCost EstimateDate of Last Estimate
ROW (Right of Way)1991$2,263,448.993/24/2020
PE (Preliminary Engineering)2012$9,346,598.293/14/2011
ROW (Right of Way)2020$19,070,000.003/24/2020
UTL (Utilities)2026$2,923,641.099/9/2025
CST (Construction)2026 12/19/2024
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports

 
 
 
 

Project Outreach Archive