I-75 NB CD SYSTEM FROM SR 331 TO I-285
Project ID: 713210- Notice to Proceed Date:
Project Manager: Ashley M. Willoughby Construction Percent Complete: 99.02%
Office: Program Delivery Current Completion Date:
County: Clayton Work Completion Date:
Congressional District: 005 Construction Contract Amount:
State Senate District.: 034 Construction Contractor: ARCHER WESTERN CONSTRUCTION, LLC
State House District: 060, 074 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
This project proposes to develop a C-D roadway adjacent to northbound I-75 that would service the I-75 at I-285 interchange. The proposed project would begin along I-75 at Forest Parkway Interchange and extend approximately 2.0 miles to I-75 at I-285 Interchange. Multiple improvements are also included under this proposed project. These improvements include reconfiguration of the Forest Parkway at I-75 Interchange ramps and the I-285 at I-75 Interchange ramps, operational improvements to the I-75 corridor between Forest Parkway and I-285, and reconfiguration of the Frontage Road along the east side of I-75. In summary, approximately 3.26 miles of interchange ramp modifications and new collector-distributor adjacent to northbound I-75 connecting to Forest Parkway and I-285 in Clayton County.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)1995$1,717,497.024/9/2013
PE (Preliminary Engineering)2014$1,796,209.134/9/2013
ROW (Right of Way)2016$4,202,400.0012/4/2015
CST (Construction)2019$81,558,258.0410/10/2018