I-16 EB FROM I-75 TO WALNUT CREEK - PHASE IV
Project ID: 311005- Notice to Proceed Date: 6/21/2021
Project Manager: Cherral Marie Dempsey Construction Percent Complete: 78.33%
Office: Program Delivery Current Completion Date: 1/10/2025
County: Bibb Work Completion Date:
Congressional District: 002 Construction Contract Amount:
State Senate District.: 025, 026 Construction Contractor: WEBBER, LLC./UNITED INFRASTRUCTURE GROUP, INC.
State House District: 143 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction
Right of Way Authorization: Contact Us
Project Description:
Phase 4 consists of 2.92 miles of capacity and operational improvements to I-16 eastbound from I-75 to Walnut Creek (milepost 0.00 to 2.92). Second Street will be widened from four to six lanes, and the Second Street overpass bridge will be reconstructed. A 10 foot sidewalk will be added to the east side of the Second Street bridge. Eastbound entrance and exit ramps will be added to Second Street with this phase. The Phase 4 improvements will complete the ultimate build-out of I-16 eastbound started with Phase 1. Within the main interchange, Phase 4 will also construct the remainder of the south-to-east ramp from Phase 3 and the remainder of the west-to-south ramp and north-to-east CD road from Phase 2.
ActivityProgram YearCost EstimateDate of Last Estimate
ROW (Right of Way)2011$1,956,080.52 
CST (Construction)2021$149,006,176.02 
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports

 311005-_L&D_ADVERT_OCT2010.pdf
 311000-_311005-_311400-_311410-_REVCR_Letter_MAR2013.pdf
 311005-_REVCR_SEP2010.pdf
 311005-_L&D_SEP2010.pdf

Project Outreach Archive

 AREA MAP.pdf
 DISPLAY3.pdf
 HANDOUTS.pdf
 Powerpoint Presentation.pdf
 DISPLAY2.pdf
 DISPLAY1.pdf