CS 1985/MITCHELL STREET @ SOUTHERN RAILROAD .2 MI W OF SR 3E

Recovery.gov
   
 
Project Image

Project Description

The proposed project would replace the existing Mitchell Street Bridge located over CSX Railroad between Techwood Drive and Spring Street. The existing bridge is in need of replacement due to inadequate load limits and a low sufficiency rating of 38.1. The bridge was constructed in 1924 and reconstructed in 1940.  The bridge functions not only as a major connecting route into the city from the west for regular vehicles, but also supports transit buses. This project would replace the deficient structure with a bridge to meet the load limits and bring it up to current standards.The purpose of this project is to correct bridge deficiency, serve the transportation demand generated by the increase in employment and through traffic, and improve the safety of the roadway.

Project Details

Scheduled Start Date
January 05, 2010

Scheduled Completion Date
September 29, 2012

Stimulus Funds Expended To Date
$8,559,195

Number of ARRA Contractor Employees This number only reflects the total number of workers on this project for the previous month as reported to GDOT by the contractor, including any subcontractors, and is not the cumulative total for the life of the project.
0

Economically Distressed Area
No

Contractor
ARCHER WESTERN CONTRACTORS, LTD.

Project Cost
$10,273,563

County
Fulton

State Project Number
752520-

Project Type
Bridges

 
   
 